- Eaves installed and painted to whole of house (bar front elevation)
- Rear upper wall second render coat applied and Rampart colour applied (not sure if this is painted over the render or a part of the render colour)
Also received my weekly update from my BC informing me of the following (lets see how close to these dates everything goes):
- 25/05 - Framer back to install rear roof and garage roof
- 29/05 - Roof completed (assuming this means colourbond and sarking installed)
- 30/05 - Insulation installed
Rear Upper Wall Painted - Rampart Colour with White Eaves (600 wide)
Another view of the rear upper wall and eaves
Picture taken from the reserve looking at the rear of the house