Happy to find the Hebel completed, with the renderer having completed their first coat of render to around 80% of the house.
A list of things I'm still waiting to be completed:
- Rear extension roof trusses (waiting for scaff to be removed)
- Whirly bird missing (SS is getting plumbers back to install)
- Plumbing for floor mounted spout still not corrected
- Rumpus room replacement window to be installed (has been delivered, will probably get installed when framer comes back to do trusses)
- Some cables (speaker wire, ethernet) not run in some locations
- Cavity slider and bulkheads missing (will be installed when framer comes back to do roof truss)
- Garage roof 80% done (scaff in the way and will be completed by framer when scaff removed)
- Colourbond roof installed to Garage and Rear Extension
- Internal Garage door replaced (will be done by framer)
All in all, framer has a few odd jobs to be done over the next couple of days when he is on site next. I have been promised this was to be done Saturday last week, still wasn't done this Saturday, so will be asking SS for a revised date (third time lucky), but I would say this was delayed as he couldn't do the big job while the scaff was in the way.
Some snaps of the house as it stands from the weekend (before renderer came).