A few teaser pictures for the followers before we get more from our PCI visit.

As other blogs mention, things seem to be on GO SLOW MODE.

Things that have been done this week:
- Additional minor electrical fit offs
- Some missing tiles fixed
- Caulking in wet areas
- Cornice installed in Master Ensuite
- Handles installed on drawers (we opted to doors to be left as we changed our mind and want knobs not handles and as PD will not swap we thought it easier to leave them off)
- Render applied to remaining facade (which has run in some placed due to rain)
- A few exterior dents touched up
- Bathroom fit offs (toilets installed etc) 

Things that are pending:
- Master bath still to be installed
- Paint Cornice
- Install Carpet (this was due to be done 07/08)
- Mirrors and shower screens delayed to the 20th (1 day before forecast handover)
- Some handles missing on cavity sliders
- Stairs to be painted/stained
- Touch ups (holes mended, paint spots, clean etc)
- Install electrical items (oven, HWS etc)